Is there a way to add the total estimates of all the stories/tasks in the sprint bar? My teams are asking for a way to know how the sprint looks once all the tasks are estimated.
It would be nice if this was default behaviour or a plugin was added. You could add a feature request at https://jira.atlassian.com
The way I do this right now is to add the orig estimate column in the issue navigator and move it over near the start. That way a tot up can be done easily enough, see the screenshot on https://answers.atlassian.com/questions/88372/sum-of-original-estimate-in-issues-by-filter