Per Lundevall April 22, 2022

I realized I have closed a sprint before I put issues in the sprint to Done. This is impacting my velocity count for that sprint. Do I need to reopen the sprint and set the issue to Done and then close the sprint to get the correct velocity?

1 answer

0 votes
Dave Mathijs
Community Champion
April 22, 2022

Hi @Per Lundevall , welcome to the Atlassian Community!

When you complete a sprint and it has incomplete issues, there are 3 options:

  • move the issues to the backlog
  • move the issues to any future sprint that's already created
  • create a new sprint and then move the issues to the new sprint.

Which option did you choose when you completed the active sprint?