Done tasks disapear from Roadmap

Yana Baklaikina September 6, 2023

Hi, community!

Have a problem with tasks in roadmap. When task get status closed or close (cancel) it disappear from roadmap immediately. Exclusion rules 30 days. I can still see task on a board and in project. There are several screensBoard.pngProject.pngRoadmap.png

2 answers

1 accepted

1 vote
Answer accepted
Yana Baklaikina September 11, 2023

Hi, Thanks for answer, but problem was in enother place. I should to add post function for status "closed" 

Post function.png

0 votes
Marc - Devoteam
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 6, 2023

Hi @Yana Baklaikina 

This is default behaviour.

A roadmap is based upon a project, board or filter. To keep to overview usable the default exclusion setting on a plan is 30 days. 

It represents issue that are in Jira

This can be adjusted.

A board on a Jira project by default has a setting that "Closed" issue are on the board for 2 weeks after entering the "Closed" state.

This setting can also be changed.

Done issues will always be present is the system.

Issue don't get removed from the system when set to "Closed".

Docmaster CCS
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
September 13, 2023

I have arranged the issues on my board as per status. And I see 0 issues under DONE. As per the above, I can change this. Can you please show how?