Good afternoon!
I have structure in Jira with some columns, both of them - create date and done date.
Structure looks like: task -> subtask
I want to duplicate date of create task to subtask in another column, how to do that?
Thank you
Hi @Rkeanefootball1! ,
Welcome to the Community!
Could you share a little bit more about your goal? It sounds like you want to add a new column to the structure where the Task (parent) created date would show at the Sub-Task (child) level. Is this correct?
Also, it would be good to know for sure if you are Cloud or On-Prem hosted. A quick way to check is if you see a button for Automation or Show Generators in Structure. Automation would indicate on-prem and Show Generators cloud.
Best,
David
Hi @Rkeanefootball1! I don't know what is the purpose but from my point of view:
- If the subtask is created manually -> must update the data in the database(not recommended)
- If the subtask is created by the customized code/ scripts -> we can use created date time from the parent task and set it to subtask
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.