Dynamic Date is not working in The Scheduler

Susan Hauth _Jira Queen_
Community Champion
May 9, 2019

Our field "Implementation date and time" (date/time picker) we want to set it 5d 18h from the creation date of the scheduled issue.

However we're getting really weird dates set based on that:

The issue that was created from the scheduler ended up with this weird date:

image.png

THere were no updates to the Implementation Date and Time that's what the scheduler put in.

Here's how the Implementation date and time field was configured in The Scheduler:

image.png

2 answers

0 votes
Lucas Modzelewski _Lumo_
Atlassian Partner
May 20, 2019

Hi @Susan Hauth _Jira Queen_ ,

Take a look at the example next to input "m" is treated as month, if you would like to use minutes use "min"

Please check if thats the case :)

Cheers,

Łukasz

PS. Our recommended support channel is our Customer Portal: https://psc-software.atlassian.net/servicedesk/customer/portal/10 

0 votes
Deleted user May 9, 2019

Hi there,

I just wanted to confirm if you're talking about "Automation for Jira", or "The Scheduler"? Since this question was fired under Automation for Jira: https://marketplace.atlassian.com/apps/37456/the-scheduler?hosting=cloud&tab=overview.

Susan Hauth _Jira Queen_
Community Champion
May 10, 2019

Oops....got the wrong tag...I have updated it thanks...