EasyBI - Issues closed/resolved vs Sprint issues completed

Derek Knudsen September 16, 2024

 

Hey all. Building a basic report to show average cycle time for sub-tasks for a specific developer for each sprint. I am running into an issue where not all the issues the developer did in the sprint are being included. To get a sense of what is happening I added Issues Closed and Issues Resolved Measures as well as Sprint Story Point Completed. The latter shows all of the items the developer worked on but the former measures appear to just be a subset of that list. In looking at the individual tickets of both I can’t figure out the difference. They have identical Status and Resolution. Anyone have insights?
Screenshot 2024-09-11 at 3.34.41 PM

1 answer

0 votes
Paul O
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 21, 2024

I suggest you check which statuses you have defined as 'closed' in your EazyBI instance

The issues closed measure is defined in your settings - see here. It is a count of issues in the statuses listed in this setting

Sprint issues completed counts the number of issues in the done status category at the point the sprint was closed. 

 

 