Hello,
I am encountering an issue where the green progress bar in the epic panel only updates when issues are marked as "DONE" but not when they are marked as "ARCHIVED." I have ensured that the resolution is set correctly for both statuses, and both are categorized as "Done." Despite this, the progress bar does not reflect the updates for the "ARCHIVED" status.
Additionally, the progress bar only turns green when tasks are moved to the rightmost column, ignoring all suggested settings and configurations, no matter how many times they are implemented. Here are the steps I have taken so far:
Despite these attempts, the progress bar still does not update for the "ARCHIVED" status. It only updates when tasks are moved to the rightmost column. Could you please assist in resolving this issue so that the progress bar updates for both statuses?
Thank you.
Hi Mladen
It sounds like you are using a scrum board. And indeed, only issues that are in the far right column are considered completed. This is by design for this type of board.
Therefore, you need to map the Archived status to the last (far right) column.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.