Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Error when changing the Target Start field

Alexandr August 23, 2024

Errore Target Start.pngTarget Start OK.pngI encounter an error when trying to change the value of the Target Start field by moving the slider: "Cannot change manual start date. Unable to change task Start Date ("Target start" field update error). Please check Jira configuration." If I manually change the field and select a date from the calendar, the error does not occur. How can I fix my issue?

1 answer

0 votes
Stepan Kholodov _Tempo_
Community Champion
September 24, 2024

Hello @Alexandr 

Recently, there was a bug related to Target start/Target end dates fixed in Structure. Please try to upgrade both Structure & Structure.Gantt to their latest versions and see if it helps. The fix was introduced in Structure 9.4.

If you still get the error after this, please reach out to us directly at our support portal.

Best regards,
Stepan
Tempo (the Structure app vendor)

Suggest an answer