I have a scenario
I want to create an epic in that epic I create some tasks automatically and name them
tasks 1
task 2
Now I want to automatically fill the original estimation for these tasks so nobody can change that
for example when task 1 created the original estimation for that task will be 5h (automatically filled)
task 2 created original estimation will be 3h(automatically filled)
so assign user can only put the hours spend on that tasks
I dont know how can I achived this.
I am using jira cloud
You can use Automation to accomplish this with one exception. You can’t prevent someone from editing the OE at least not natively. Below is a concept on the rule but I would need more details to get closer. You could actually create a manual rule to create your epic and tasks if desired.
trigger - issue created
condition - issue type equals Task
condition - epic link equals xxxx or epic link is not empty
action - edit issue , original estimate equals xxx
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.