Jeroen Houwen September 21, 2015

I added the status 'Deployed' and ´Released' to the workflow so our customer can see where he can check his issue. Now i read i had to put the 'done' column at the end because otherwise all done issues are in the backlog. But now the issues with released and deployed status are seen in the backlog... I can not change the filter for the board becase than the issues are also not vissible in the sprint...

Is there a workaround to use different status that behave like 'done' in the last column for JIRA Agile board?

@nic Thanks, but i do like to have them in separate columns, is that possible?

1 answer

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 22, 2015

Assuming Deployed and Released are end-status (i.e done), just change the board definitions - put the two status in the "Done" column on the far right along with whatever status is already there.

Jeroen Houwen September 24, 2015

@nic Thanks, but i do like to have them in separate columns, is that possible?

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 24, 2015

Yes, but then they're not "done"