I need my sub-task to inherit its fix version from its parent. I tried doing it via automation but somehow its not working. I need help with creating this automation rule.
Sub-task - fix version field should populate based on its parents fix version field.
Hi @Spruha Shah ~ you should be able to use the "COPY" option in the Edit Issues action in your automation rule as shown below....