Hello everyone!
In the attached screenshot you can see the settings I have entered within BigPicture, which allow me to enter just "start date" and "original estimate" when I create a task, and automatically have the end date calculated, taking into account also holidays and weekends.
I would like to change the original estimate at a later time (after creating the task) by keeping the duration of the task unchanged.
Is it possible to do so in BigPicture (non Enterprise)?
Thank you in advance!