When setting up work for PI planning, we don't have a way to map out our PIs according to actual PI dates. So when viewing the roadmap, our features don't align to a specific quarter. Currently, we designate a PI by adding a label to a custom field. I know there is a better way to do this. What solutions have you guys used for this scenario? Thank you.
Hi @Cassandra Fitzgerald Medley and welcome to the Community!
You might consider using Releases to represent your PI's. They are an out if the box feature in Jira and they have a start and end date associated.
You can find a bit more information through this support article.
Hope this helps!