Hi,
is there a way to forbid setting an epic/story done if the issues in the epic/story aren't done?
Regards, Ahmet
Yes, you add a "subtasks not closed" condition to the transition(s) leading into "done" status in the workflow. This is a function built into standard JIRA, and it can check any status, it's not just limited to "sub tasks are done"
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.