I have a timeline view for 10 projects grouped together. Our heirarchy is as follows:
1. Initiative
1.1 Epic
1.1.1 Task
1.1.1.1 Sub-Task
I have a label that I want to filter on. I have configured everything for the plan view, but for some reason, even though I have "Show full hierarchy" unselected, I am still getting the full hierarchy.
We are attempting to make an activation schedule for a building and ONLY want to show work items with that label and not their parent(s). If I filter out Initiatives and epics I get closer to what I want, but I also want sub-tasks to appear and NOT the parent task IF it doesn't have the label applied.
I've attached a screenshot of my filter.