I am creating a new KanBan Jira project from scratch and have created epics w/ tasks that have "Start" and "Due" dates. However when I view the "Roadmap" there is no visual "Gantt". The roadmap appears with the epic "rows" on the left, nothing appears on the right in the monthly columns? What do I have to do to get the Epics and Tasks to appear there?
Hello @brad_gerard
Welcome to the Atlassian community.
If you are accessing the Roadmap option from the navigation panel for the project/board then you are accessing the Basic Roadmaps functionality.
This document details how to schedule issues for a Kanban board for basic roadmaps:
Thank You @Trudy Claspill! This is exactly what I was looking for.
1) In Roadmap I went to top right "3 dots" > Configure Roadmap
2) Checked the "Child-level issue scheduling" which shows schedule lines as desired
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.