Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Greenhopper Story View

AgilePM
Contributor
May 23, 2013

Hello - I know Greenhopper is mostly useful for developer to manage subtasks related to a story, however is there a way to create a greenhopper view where Subtasks are hidden and Stories appear as cards in Greenhopper?

We have built two workflows. (1) for Stories and (2) for subtasks. We want to see where stories fit into the buckets that Greenhopper provides (e.g. ToDo, In Progress, Done) rather than just see the story span accross all three buckets as a container for Sub Tasks.

1 answer

1 accepted

0 votes
Answer accepted
AgilePM
Contributor
May 23, 2013

I think I might have answered my own question (lol) but I will keep it open if someone else wants to provide more detail or a better solution.

In the Greenhopper board configuration (Tools > Configure) select No Swimlanes

Suggest an answer

Log in or Sign up to answer