Help me understand Time Tracking Report (Accuracy)

Sebastian Somi
Contributor
March 29, 2023

Hi, 

I understand that for the top column the accuracy of -1d3h is result of 1d estimate - 2d 3h time spent.

 

What is the logic behind the bottom red rectangle?

 

Because - 5h does not equal 4h original estimate - 6h time spent.

 

image.png

1 answer

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 29, 2023

Hi Sebastian,

It takes into account the estimate of the time remaining too.

In this case, you have:

  • Original estimate: 4h
  • Time remaining: 3h
  • Time spent: 6h

It's a bit convoluted, but think of it as

We've done 6 hours on it, we've got 3 remaining, so the estimate-to-complete is now 9 hours. 

We originally estimated 4 hours, so 9-4 = an underestimate of 5 hours.