Help with Items added to a Burn Down...

Capo Di Tutti March 14, 2022

Background: My project is tracking Action Items (running man icon) along with Stories, for an overall project work view for each section of the project.

I've built dashboards by subject area / managed by a team member. I have been able to get Action Items to show up in my  "Items in current sprint" break out at the bottom of the page. This list view used to match the burn down we have at the top of the page. So 10 Stories show on burn down then 10 Stories show on my list view. 

Issue: Through adjusting my query, I can see both Action Items & Stories in my list view which used to give more thorough explanation of the simple number items in the burn down. I cannot for whatever reason, get the burn down to reflect the same items,it only shows stories.

Solution?: Does anyone know what I might be doing wrong? Or do I need to have a different type of burn down chart?

1 answer

0 votes
Ste Wright
Community Champion
March 27, 2022

Hi @Capo Di Tutti 

Burn downs should show any Issue Type - assuming...

  • they're all available in the same Scrum Board,
  • aren't filtered out,
  • and have the appropriate estimations added (if not set as a count of Issues).

^ Could you provide some screenshots, to better detail where the error is happening?