How are *commitment story points* calculated for a *Sprint*

Meenakshi Khanna July 24, 2018

How does one calculate commitment story points for a sprint.
Velocity chart shows 139/160 story points but sprint details show
128-->139 completed, 44 Not completed, 24 Removed.
As per my calculation, Commitment SP for Sprint should have been ( 128+44+24=196 ).

2 answers

1 accepted

6 votes
Answer accepted
Tarun Sapra
Community Champion
July 25, 2018

Hello @Meenakshi Khanna

In the docs it's pretty clear as to what exactly committed points means for velocity chart

  1. Commitment: The gray bar for each sprint shows the total estimate of all issues in the sprint when it begins. After the sprint has started, any stories added to the sprint, or any changes made to estimates, will not be included in this total. 

In your shared data you have mentioned 44 points are "not completed" and 24 as removed, but were any of the issues from these 2 sets added after sprint start? Because if they were added after sprint start and later removed or left incomplete then they won't count towards the "committed" total of 139.

Meenakshi Khanna July 25, 2018

Thanks Tarun for your response.

Yes I checked  and found that some stories were added to sprint after sprint start.

At Sprint start Committed story points were 160 ( 44+24+92 ).

139 completed includes ( 92+47  added ones ) 

 

Thanks a lot. I am all set for now.

Tarun Sapra
Community Champion
July 25, 2018

Glad to know @Meenakshi Khanna that it's all done now. Could you please accept/upvote the answer. thanks!

Meenakshi Khanna July 27, 2018

How do I accept/upvote ?

Tarun Sapra
Contributor
July 27, 2018

image.png

 

Please click on the tick next to the answer and for upvoting you have to click on the "up" arrow sign,

Meenakshi Khanna July 27, 2018

Thx. Worked now. Uparrow Vote was not working earlier.