To make our stand ups more streamlined we'd like to be able to log time on sub tasks directly from our rapid board. How can I add this functionality? All that is currently displayed on the sub task card is summary and priority.
In the 'estimation' tab on the board configuration set the board to use 'Original Time Estimate' for the estimation statistic and 'Time Tracking' on.
Then in the board, if you click on the sub-task the detail view will open. In work mode on the detail view hit the '+' sign next to the remaining estimate lozenge to log work.