How can I change date format from "dd/Mo/yy" to "yyyy-mm-dd" in JIRA Project timeline view?

정DY
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
March 19, 2024

Using Jira Software,

How can I change date format from "dd/Mo/yy" to "yyyy-mm-dd" in JIRA Project timeline view?

(1) Date format on "Project Timeline View" : "dd/Mo/YY"

스크린샷 2024-03-20 090911.png

(2) Date format on "Issue Navigator View : "yyyy-mm-dd"

스크린샷 2024-03-20 092236.png

1 answer

0 votes
Kseniia Trushnikova
Community Champion
March 22, 2024

Hi @정DY,

Currently, the date format in Advanced Roadmap plans is not configurable.

Though, there's the open suggestion https://jira.atlassian.com/browse/JSWSERVER-24538 to provide users the ability to change the date format. You might want to add a vote for it.