How can I change the priority of a subtask that I created?

Reth August 7, 2023

Hi everybody,

for a task in our JIRA I created a subtask and filled in all relevant fields. Unfortunately there is no possibility to chang the priority during subtask creation nor afterwards since this field is not shown - neither during creation nor when editing the subtask.

Also the priority of the parent task is not automatically taken over but the subtask got created with lowest priority.

The only workaround I could find so far is to start a bulk operation, select the subtask in question, then select edit and afterwards select priority field and change its value.

But is there really no easier way to change the subtask priority?

 

Thank you in advance for a short reply and

Kind Regards

3 answers

2 accepted

2 votes
Answer accepted
Manoj Gangwar
Community Champion
August 7, 2023

Hi @Reth ,

You just need to add the Priority field under Subtask Issue Type Edit Screen after that It will be editable for you.

Go to the project setting>>Screens>>Subtask Issue type Screen>>Edit Screen>>Add Priority field.

0 votes
Answer accepted
Mohanraj Thangamuthu
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
August 7, 2023

Hello, On the sub-task you will have the option to change the priority as shown in the image. If the field is not editable then you need to check if priority field is added to edit screen as well.

 

Screenshot 2023-08-08 at 10.34.07 AM.png

0 votes
Reth August 8, 2023

Thank you. So seems I need to talk to our admins then - cannot edit these settings myself.

Field is read only for us.