How can I display report with difference between origin estimate and timespent?

Christina Zhanko
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
May 10, 2018

How can I display report with calculated   difference between origin estimate and timespent for every task of choosen user?

1 answer

0 votes
Walter Buggenhout
Community Champion
May 10, 2018

Hi @Christina Zhanko,

When you perform a search in issue navigator, adding the column Work ratio gives you a clear indication of where you are on each task. It is a relative measure though (in %), not an exact calculation. But maybe that covers your main need.