Hi,
I want to group my Epics into business objectives and generate weekly reports. I figured that Portfolio is a good place to do that and you can group by Themes over there. These Themes are business objectives/ groups in which I want to track progress.
I changed the portfolio interface to the old version so that I can see reports by themes. So far so good.
But when I go out of Portfolio to my Issues list, Backlog etc., the Epic/Theme column doesn't populate with the Themes I set in Portfolio. The column keeps saying 'None'.
I can use Labels to tag Themes. But then reports in Portfolio can't be filtered by Labels.
Is there a way that the Epic/Theme column can be populated - or better - it reflects the Themes I set in Portfolio?