How can I make sure an user closes sub-tasks before closing the main task

Jux
Contributor
June 25, 2019

Currently I noticed that some of the assignee close a task without closing the sub-tasks. Can't seem to find a way to lock the task closure until all sub-tasks are closed.

 

So currently I am working on instilling discipline but wondering is there a way to make sure that happens on Jira?  

1 answer

2 votes
Alexey Matveev
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 26, 2019

Hello,

Use the Sub-Task Blocking Condition. (go to workflow -> conditions)