Hello Team
Is there a possibility to view the percentage of completion of work on each user story or task based on the worked hours logged by each user. I have been asked for this report by my superiors. Please advise
Thanks.
Shailaja Tadla
Hello @Shailaja_Tadla
The Work Ratio field will show you the percentage of time logged comparing Time Spent to Original Estimate. If you have multiple people logging time against a single issue it won't show you values per user, but rather just overall for the issue.
In a Company Managed project you can also add the Work Ratio field to Card Layout to show it on each card.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI @Shailaja_Tadla If you add an Original Estimate to you issue, then original estimate - time spent = remaining estimate. This is not displayed in percentage, but in days/hours.
Third-party apps may feature the progress in percentage based on hours, not based on resolution.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.