Hello all,
I would like to see the done items have been completed in a sprint. I cannot have sprint report since it's a team-managed project. Therefore, I need to filter them.
When I filter with a sprint value, it shows me the issues contains that sprint and the next sprint in addition to the issues that completed in that sprint. Here is the example attached;
I would like to see the issues completed in Sprint 82 but there are the items completed in Sprint 83 as well since they were not completed in Sprint 82.
Hi @Berkan Suna ,
In a team managed project, you can use the Sprint Burndown chart report to get the information you want. Below the chart, there are a few lists with issues, one of them being the list of issues completed in the sprint.
With that list comes a link to view the issues in the issue navigator. And then from there, you can export the issues to e.g. Excel.
Hope this helps!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.