I'd like to set the 1-week sprints for my project and then modify the start end dates for each - how do I do this, please?
Hello Parag,
Thank you for getting in touch with Atlassian Community!
You can change the start and end date of a sprint through the backlog.
Please, go to the backlog and on the ... click on "Edit sprint", change the dates and click on "Update".
Hope this helps!
Regards,
Angélica
Thanks but when I click on 'Edit Sprint' I get the attached:
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Parag,
Thank you for the details.
Are you using Next-Gen or Classic project?
Are you the only user facing this issue?
Was there any change before this issue happens?
Regards,
Angélica
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.