How can I update the configuration of a Burdown Chart?

EL ASSALI Meryam April 19, 2023

Hello, 

 

I would like to make my burdown chart based on the status "Test Ok" but not the status "Done". 

 

How can I proceed? 

 

Thank you

1 answer

1 vote
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 19, 2023

Welcome to the Atlassian Community!

Reconfigure the board the burndown chart belongs to.  Put "Test ok" in the very last (rightmost) column on the board.  Then make sure "done" is in a column before "test ok"