Hello,
I would like to make my burdown chart based on the status "Test Ok" but not the status "Done".
How can I proceed?
Thank you
Welcome to the Atlassian Community!
Reconfigure the board the burndown chart belongs to. Put "Test ok" in the very last (rightmost) column on the board. Then make sure "done" is in a column before "test ok"