How can we create an epic link in a team-managed project such that, when the epic link is selected in a task, the parent issue automatically updates to reflect the epic that was chosen in the epic link?
Hi @Samuelraj - Team-managed projects do not use epic link. They use parent. To make sure I'm on the same page, you're trying to accomplish something like this:
If this is what you're trying to achieve, you can use automation to accomplish it. Using the example above: