I added the 'Due Date' field to my default Issue Screen. I can see that any newly created issue in my project now includes 'Due Date', but that field does not show up for existing Issues.
Why? And how can I include it?
Click "edit" and put data in them. JIRA hides fields from the issue view if they are empty.
Hi Robb.
I´m pretty sure it´s not included in existing issues because Due Date field is empty.
Try to edit one of the existing issues and set a Due Date and then visualize it.
Regards! Aylin.