Hi there,
I would like to be able to split the backlog items into key sections. Here's an example of what we wish to achieve:
How can I do the above using a Scrum/Kanban board?
Thank you in advance!
There's no specific functionality to split a backlog into multiple pieces - the intent of the backlog is to house work which is not started.
I appreciate these statuses are non-working statuses - I guess it depends on how you measure progress.
There are a few options I've seen used in the past:
Multi-Board:
^ This allows for multiple "Backlog" views. The last column / first column becomes the conduit between the two boards to show completion in one and commencement in the other. So in your instance:
Scrum Backlogs:
^ This uses the sprint option to break-up the backlog and still allows you to use Kanban if you prefer over Scrum using an active sprint as the conduit between backlog and board.
For this option, just bear in mind your reporting is likely to be less useful - so might need to report externally using the data.
Ste