I have a series of issues in my structure gantt chart linked together by dependencies so that the next one starts only after the previous one finishes. The last issue on the "chain" is linked to a task turned to a milestone with the same dependency. However, when there is a conflict issue, I do not want the milestone to move/change its date, but the issues to adjust. Simply said, I want the milestone to have maximum priority during the scheduling conflict, and the issues to change their start and end date. How do I achieve this?
I also tried it with FixVersions. However, no solution was found.
Thanks!
Hello @Salkan Avdic
The described is not possible - there is no 'backward' scheduling logic in the Gantt Charts app. If there is a scheduling conflict, it is always resolved by rescheduling tasks forward.
However, we do have a feature request in our backlog to make something you described possible. I will add your vote to the feature.
If you have other questions about Structure, please reach out to us directly at our support portal.
Best regards,
Stepan
Tempo (the Structure app vendor)
To create a dependency between a milestone and an issue, you can link the issue to the milestone in your project management tool. Prioritize the milestone by adjusting its settings or using specific labels that indicate its importance. Ensure that team members are aware of this dependency to align efforts accordingly. If you need specific instructions for your tool, please provide its name!