How do I get the hour burndown to inlude sub-tasks?

Ashley Jean July 25, 2016

My team is estimating and logging time on subtasks. In the story, I can see the time rolled up from the sub-task as expected. How do I get the burndown chart to include the estimate and logged hours for subtasks? Currently, most show as 0 because the info is in the sub-tasks.

1 answer

1 vote
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
July 25, 2016

Code - you need something that can duplicate the sub-task information and add it up on the parent.

There are a couple of add-ns that do just that I believe, in the marketplace. 