Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

How do I make date bars appear in the Gantt chart in Advanced Roadmaps?

Jeff Davis
Contributor
February 7, 2023

For my project's Jira issues, teams are filling in the Start Date and End Date for each issue. The Gantt chart dates seem to be driven by Target start and Target end (those column headers each have a D beside them). The date bars will show up only if I manually plug in the dates in the Target date columns, even though they are already in the issues themselves by virtue of Start Date and End Date. Thing is, I was using Target Start and Target End before, and date bars didn't show up then, either.

I need the Gantt chart to automatically show the date bars, timeline schedule bars, whatever the heck they're called, without making my product managers and product owners plug in the dates themselves into the plan after they've already put it into the issues. I thought this functionality was in Advanced Roadmaps.

Which date fields should we be using? Within my project's issues, do I need to migrate data in Start Date to Target Start and the data in End Date to Target End? Will that make the date bars appear in the Gantt chart? EDIT: I tried that, it didn't work.

Step-by-step instructions would be appreciated. I'm on Jira Server 8.20.10 and Advanced Roadmaps 8.20.10 in a classified environment, so I cannot share screenshots.

Thank you in advance for any help you can provide.

3 answers

1 accepted

0 votes
Answer accepted
Jeff Davis
Contributor
March 2, 2023

After speaking with a colleague, I found the answer. This requires Advanced Roadmaps.

1. In the Plan view, click the gear icon at top left.

2. Click Configure.

3. In the left pane, under General, click Scheduling.

4. Under Dates, choose the date fields you're using for start and end dates in your Jira issues to display those issues' timeline schedule bars in the Gantt chart.

0 votes
Chris Mills
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
September 8, 2023

Hi Jeff

I was just trying to figure this out, and I came across your post. I couldn't find the Plan view, but I did find the three horizontal dots on the top right of the timeline, next to 'Export'. It has one menu item, 'Configure Timeline'. 
Under this there is a single toggle to turn on the schedule bars for all sub-issues. 


0 votes
Jeff Davis
Contributor
February 16, 2023

Does anyone have any ideas?

Suggest an answer

Log in or Sign up to answer