How do I monitor how long items take to complete?

Marc Taylor November 20, 2018

Hi, hoping you can all help. 

 

I want a report that tells me how long an item took to resolve from when we started working on it to when it was resolved. I don't want the clock to start ticking until the item moves into an 'in progress' state. I don't want the report to calculate the time from the 'date created' field, I want it to start when the status is changed to 'in progress' (or an alternative status we have in our workflow). 

 

This seems like quite a straight forward report that most people would want, I feel like there must be an obvious solution which I can't figure out! 

 

Thanks 

 

 

1 answer

1 accepted

0 votes
Answer accepted
Walter Buggenhout
Community Champion
November 20, 2018

Hi @Marc Taylor,

A good place to start would be the Control Chart. The report is associated with agile boards and is a really powerful instrument to drill into this type of information.

Marc Taylor November 20, 2018

This looks like what I was after! I don't know how I didn't see this report before .

 

Thanks so much for your help 

Suggest an answer