How do I query the parent issue id of a subtask?

Velina Urdova June 4, 2012

Hello,

I am writing a simple query against the Jira Database, but I cannot get the parent issue id of the issues. I tried including customfieldvalue.parentkey, but it is NULL for all the subtasks. Does anyone know what the actual parent key id is?

Thanks,

Velina Urdova

1 answer

1 accepted

0 votes
Answer accepted
Jobin Kuruvilla [Adaptavist]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 4, 2012

You should be looking at issuelink table. Subtasks will have a link to parent issue with link type as 'jira_subtask_link'. You can find the id of linktypes from issuelinktype table.

Velina Urdova June 4, 2012

Thank you very much, Jobin!

DIOUF Abdou Karim
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
September 28, 2017

Hello all,

I came across this thread because I am trying to get the Parent link directly out of jira database by querying in SQL. I am not able to find it. Could you please share your sql code that you wrote to get it. Thank you in advance.

 

Here is the Sql query I am writing :

 SELECT P.PNAME, I.ID, I.SUMMARY, ILT.LINKNAME FROM ISSUELINK IL
    LEFT OUTER JOIN ISSUELINKTYPE ILT ON IL.LINKTYPE=ILT.ID
    LEFT OUTER JOIN JIRAISSUE I ON IL.SOURCE=I.ID
    LEFT OUTER JOIN PROJECT P ON I.PROJECT=P.ID
    WHERE ILT.LINKNAME='jira_subtask_link'
      AND P.PNAME='XXXX'

Hung Nguyen
Contributor
April 4, 2019

I came across this too, and I saw that I had to use the following SQL instead

SELECT I.ID as "Sub-Task ID", P.Project_Key||'-'||I.Issuenum As "Sub-Task Key", I.SUMMARY as "Sub-task Summary",
P.Project_Key||'-'|| PI.Issuenum As "Parent Key"
FROM JIRAISSUE I
JOIN JIRAdbuser.IssueType IT on IT.ID = I.issueType
JOIN Project_Key P ON I.PROJECT=P.PROJECT_ID
LEFT OUTER JOIN ISSUELINK IL ON IL.DESTINATION=I.ID
JOIN ISSUELINKTYPE ILT ON IL.LINKTYPE=ILT.ID AND ILT.LINKNAME='jira_subtask_link'
JOIN JIRAISSUE PI ON IL.SOURCE=PI.ID
WHERE IT.PNAME = 'Sub-task'
AND P.PROJECT_KEY= 'XXXX'

Pretty much you have I for the Sub-Task, and PI for the Parent issue, hence you can get more information out of these if needed