Rob Marshall November 7, 2018

In my current Sprint, I defined it as 2 weeks in duration. Is it possible to change this once the Sprint has been created or can it only be defined at the time of creating the Sprint?

2 answers

2 accepted

1 vote
Answer accepted
Kimberly Deal _Columbus ACE_
Community Champion
November 7, 2018

Hey @Rob Marshall

Looking at your screen shot, you should be able to just click on the dates and edit them. 

sprint redate.png

0 votes
Answer accepted
Jack Brickey
Community Champion
November 7, 2018

yes. go to the backlog view and for the sprint click on the ellipses and edit sprint.

Rob Marshall November 7, 2018

Thanks for the quick reply.

Untitled.jpgWhen I click on the ellipses I only see the view summary of the assigned work. 

I do see that I can edit/change the Start and End dates of the active Sprint.

Jack Brickey
Community Champion
November 7, 2018

a couple of things...

  • those aren't the ellipses i was referring to BUT...
  • you appear to be on server and as @Kimberly Deal _Columbus ACE_ indicates  you should be able to click on the dates

in cloud there are ellipses to the far right of the sprint 

Rob Marshall November 7, 2018

Right. Thanks both of you.