We have started using Next Gen Jira for a couple of our products and it has been a lot of relearning, which I'm totally fine with as long as features don't just disappear.
After we closed our first sprint yesterday, I noticed that I could not figure out how to get to the closed sprint. Also noticed that there is no reports section (assumed that something will pop up in roadmap).
So how do we look at sprint velocity over sprints and things such as burndowns/burnups.
Also it was very useful to see a snapshot of what stories were completed and what stories were rolling over so that we can improve that.
Also is there a way to convert a next gen project to classic? other than creating a classic project and moving everything there?
P.S: This is a next gen project, not a classic one.
To get Reports in Nextgen projects, it needs to be enabled first. Goto project settings -> Features -> Enable 'Reports'.
Now you'll see a new option called Reports in the left side nav. There is a support for the following 4 reports at the moment:
Thank you very much. Yes the options seems to be disabled by default. Thank you very much, this is a relief.