I need to update the sprint value on the Epic in JIRA 7.0.4 but it looks like once it is set, it won't let me remove or change the sprint. Other issues are hard to update too but at least those have drag and drop between sprints.
I figured this out. You can use the bulk update feature (even if it is one issue) and change the sprint value. The other option is to use the JIRA Agile REST APIs - https://docs.atlassian.com/jira-software/REST/latest/
Hi Mark,
When you assign an issue to a sprint, you actually fill out the value representing the sprint in the Sprint custom field. If you want to be able to modify or remove the sprint easily, you can add the Sprint custom field to the view and edit screens that you are using for your project(s). From then onwards, you can simply select the desired sprint for your issue from the issue screen itself.
If you're unsure which screen is being used to view or edit your epic or other issues, go to the issue you want to change. Click the Admin button and select "Where is my field?" (you need administrator permissions for this). Select the Sprint field from the list. JIRA will point you in the right direction on where you should be taking action.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.