How do i get actual story points committed in the sprint vs actual Story Points Delivered
do we have any Jquery for this.
In Velocity chart committed stories are cumulative numbers which does not gives the actual committed in the sprint.
We may have cases where a story spill overs and during that we add more story points , below example for query:
so where do we get this calculation or do we have Jquery ?
Or is the understanding incorrect ?
This is not really how sprints work. You should be trying not to have stories that "spill over", but when, in real life, they do, you don't amend estimates or sizing - the whole thing moves to the new sprint.