How do you remove issues with a "Done" status from the backlog?

Cristina Boston May 21, 2024

I'm using a Team Managed Kanban Board with a backlog and epics panel.
Both my Done Column and Done mapped status is to the far right in the column configuration.

2 answers

1 vote
Tuncay Senturk _Snapbytes_
Community Champion
May 21, 2024

Hi @Cristina Boston 

Welcome to the Community!

Currently, done issues are removed after 14 days or you can clear them manually on the board. 

clear0.jpg

 

Here you can watch / follow the issue to make it customizable.

I hope that helps!

Cristina Boston May 21, 2024

Thank you :)

 

0 votes
Sudarsana G
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
May 21, 2024

You can use a JQL query to exclude "Project = xyz and status != Done and remove Done column from board level 

Cristina Boston May 21, 2024

Thank you also :)