Sprint was accidentally changed to active. How do we move it back to inactive?
you technically can't make a sprint inactive. What you can do is to stop the sprint which will push all of the incomplete issues to the next sprint. If you have any issues in the 'done' right most column move them out to the left so they don't get marked complete.
Hi @Jack Brickey,
Can the sprint be re-started then, when it's actually due?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
If a sprint is stopped it can’t be restarted. We would simply start the next sprint.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This is unfortunate as it creates a lot of hoops to jump through if you start the wrong sprint by accident.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.