Dear all,
How does the sprint health gadget calculate scope change if my team estimate in real time not in story points?
If some tickets will not be finished in a sprint and I want to do them in next sprint I have to change their date to make a statistic correct?
Thanks,
Paulina, I could not understand when you said, Estimate in real time and not in story points. If it means, in hours, then I would suggest to change the estimation in board to "Remaining Estimate and Time Spent".
Hi @Paulina Mijal ,
Essentially, there is no scope change. The scope remain the same but in your case the team did not complete the scope given. So, when you move the tickets, it becomes part of the scope for the upcoming sprint.
-Ben
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.