I want to migrate approx 5000 Bug list from FogBugz to Jira. Before I start the migration project; I want to estimate the time and effort.
This does depend on a few things such as:
^ You need to know what data you want to migrate and into what structure in Jira - as the two platforms do vary.
Based on the above it could be a matter of hours right up to a few days I would imagine. But if it was a simple export / import with all completed mapping it could be done pretty quick :)
Ste
There is effort and duration. Effort might be 1-2d but duration maybe 5d. The duration considers trial and error, designing projects, clean up, etc. getting the issues imported would only be a few hours. My point here is to plan for a week to go live.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thank you so much Ste and Jack! This helps me to have some timelines planned. I will write to you once I have a definite approach to migrate these instances. Thanks once again!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.