How to Archive "DONE" JIRA Tickets?

Frank Bartkus
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
December 17, 2019

Any thought on moving a "Done" completed ticket from an active "Client Assignment " to another location to segregate the ones currently working?

1 answer

0 votes
brbojorque
Community Champion
December 17, 2019

You can only "archive" a project in Jira.

What you can do is update the JQL or your filters to remove the completed tickets.

Or you can bulk edit the complete issues in the project and change the security level so no one can access it.

In my experience viewing old tickets is beneficial so we can track the history of whatever the things you are working on in the past.