Greetings,
We have multiple projects on Jira.
The working hours of these projects are between 09:00-19:00 (10 hours)
However, in some of our projects 8 hours = 1 day on clockworks, while in some projects 10 hours = 1 day.
How can I organize this ambivalence? Where can I edit it?
Welcome to the Atlassian Community.
The time tracking is global and affects all projects. If you need different configurations for different projects, you will need to manage this through other mechanisms like custom fields or third-party plugins that allow project-specific time tracking settings. See https://support.atlassian.com/jira-cloud-administration/docs/configure-time-tracking/ for more details.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.