Roger Porter November 16, 2017

Hi,

On the time board you have To Do, In Progress, and Done. Is it possible to add In Test before Done?

Thanks,

Roger

1 answer

1 vote
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 16, 2017

Software Boards (Scrum and Kanban) are configurable and you can add columns under "board configuration -> columns".

Core boards follow your workflow - add a status to the workflow, and it will appear as a column.

Roger Porter November 16, 2017

Hi,

Thanks for the reply. I have added a status to my workflow called 'In Test' and assigned open to it. How do you change the order of the status's? I want my 'In Test' to be before 'Done'.

Roger

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 16, 2017

Status don't really have an order in a workflow, the paths between them define what order you can move through them in (or back, or around).

On the boards, you would add a column for "in test", map the status into it and then move it by dragging the column tops around in the board configuration