How to add tab to existing tickets?

shiva shanker October 1, 2021

I want to add a tab called schedule and in that i want to add baseline start date, baseline end date , forecast start date & forecast end date.

1 answer

2 votes
Mayur Jadhav
Community Champion
October 1, 2021

Hi @shiva shanker 

Welcome to the Atlassian Community!!!

Yes you can add tab and then in tab you can add fields in it.

Here is the link of official Atlassian document for how to add tabs. https://support.atlassian.com/jira-cloud-administration/docs/manage-issue-screens/

 

Thanks,

Mayur

shiva shanker October 4, 2021

Thanks for help

Mayur

Mayur Jadhav
Community Champion
October 4, 2021

Hi @shiva shanker 

If the answer is helpful please hit accept ✅ so that user's can find helpful solutions to the problem